Grimoires Meeting 16 May 2005
Current progress so far
%ACTIONSEARCH{ within="-8" }%
Action for next meeting
%ACTION{ closed="23-May-2005" due="23-May-2005" creator="Main.LucMoreau" uid="000288" state="closed" created="16-May-2005" who="Main.SylviaWong" closer="" notify="" }% <<EOF
A78: (
WorkPlan T2.2 Integrating with myGrid. Progress: 65% finished.) Work on feta unpublication.
Outcome: finished.
EOF
%ACTION{ closed="23-May-2005" due="23-May-2005" creator="Main.LucMoreau" uid="000289" state="closed" created="16-May-2005" who="Main.WeijianFang" closer="" notify="" }% A79: (
WorkPlan T1.4 Testing and improving. Progress: 75% finished.) Address Grimoires release issues raised by Juri.
Discussed issues
In terms of Grimoires release, we will do the following work before next Monday:
- Reorganize the documentation, which will include functional spec, implementation design, test report, use scenarios, and user manual. Include the documentation in the source code release and binary release.
- Improve the usability of the junit test suite. Make it self-contained and self-executable.
- Improve the usability of Grimoires OMII release. Use AdminClient? to deploy Grimoires in OMII container.
- Answer all the questions raised in Juri's report.
--
WeijianFang - 16 May 2005